Solar Farm

Grand Island, Neb. — The U.S. Department of Energy has approved the Grand Island Utilities Department for an Energy Efficiency and Conservation Block Grant (EECBG) to the tune of $116,440.

The funds will be used to cover the cost of a five-year plan with Nelnet for both the software and equipment modules needed to monitor the solar field. Receiving the grant is not only a boost to a project that is nearing completion in December, but it’s also a boost toward Grand Island continuing to lower its energy costs.


“These funds will be an added bonus to a project that has been years in the making,” Assistant Utilities Director Lynn Mayhew said. “Our addition of a 9.9-megawatt solar farm is still on track to come online in December, which will power approximately 10,000 homes while operating at the same cost as coal energy.”